CSM Day 2 Quiz When do Individual Developers take ownership of Sprint backlog items? Selected answer: Never, all sprint backlog are owned by the entire Developers even though each one may be done by an individual Developer Clarification: There is no individual ownership for the Sprint backlog items, the whole Development Team is equally accountable for completion of the Sprint backlog items. Hence option C is correct. What is the most important characteristic of a Done increment? Selected answer: Usable Clarification: Potentially releasable increment means it should contain some business value and it should also be usable. Hence option C...